How much does an NDT inspection cost?
There is no universal U.S. NDT price list that can reliably price every job. Cost depends on the examination, the agreed billing unit, site access, schedule, qualifications, equipment and required records. Request written quotes against the same scope before comparing amounts.
This U.S.-focused guide explains how to turn a price list into a comparable quotation. It includes a method-by-method scope table, a clearly fictional arithmetic example and an RFQ checklist. The example amounts are not market rates or a supplier offer. We do not claim a proprietary vendor survey. For Canadian work, keep CAD amounts and country-specific owner requirements separate from a U.S. comparison.
If you already have rates, open the inspection quote calculator. It totals your inputs in USD or CAD and keeps the billing basis explicit. If you need a supplier, prepare the scope below before using the inspection request form.
Buying or renting an instrument instead of hiring an inspection crew? Use the NDT equipment RFQ guide to define the equipment package and approach your chosen suppliers. An equipment quotation and an inspection-service quotation describe different purchases.
A price list needs a unit and an inclusion list
Ask what the price actually buys. “One day of UT” might describe one technician with a portable instrument, or a larger crew with encoded equipment and a reporting allowance. It might cover a defined shift or a minimum callout. Do not assume that the word “day” has the same meaning across proposals.
Record the currency, rate, unit, quantity and included deliverables on one comparison sheet. Then list separately priced items. When a supplier offers a fixed project price, record the assumptions that keep the price fixed: the component count, access arrangements, working hours, surface condition and review requirements. A price can be perfectly reasonable and still exclude something your project needs.
ASNT explains that method selection depends on the material, geometry and examination objective. That means the technical scope must precede the commercial comparison. A cheaper technique is not a substitute if it cannot satisfy the required examination. ASNT: What is NDT?
What to specify for UT, RT, PAUT, MT and PT
Use this table as a starting point for the supplier conversation. It is an editorial scoping checklist, not an inspection procedure or a statement that the methods are equivalent. Have the responsible technical team confirm the applicable examination and acceptance requirements.
| Method or scope | Define before requesting a rate | Ask how it is billed |
|---|---|---|
| UT thickness measurements | Component list, measurement locations, surface condition, access and required records | Per location, hour, shift or project; identify any minimum charge |
| Conventional UT weld examination | Material, joint drawings, thickness, length, access and procedure requirements | Per weld, weld length, crew time or agreed scope |
| PAUT or TOFD | Geometry, scan plan requirements, calibration arrangements, encoded data and review package | Acquisition, setup, analysis and reporting; identify inclusions |
| Radiographic testing | Component geometry, imaging approach, site coordination and required image handover | Exposures, components, crew time or project; define repeat work |
| Magnetic particle testing | Component dimensions, preparation, examination area and restoration needs | Per item, batch or crew time; state preparation responsibilities |
| Liquid penetrant testing | Material compatibility, preparation, process requirements and cleaning responsibilities | Per item, batch or crew time; state consumables and cleanup inclusions |
For technical background, use our method library. For a proposed change involving advanced ultrasonic imaging, the PAUT, TFM and PCI trial guide helps organize a demonstration around the actual inspection task.
Choose one billing basis before calculating
A time-based proposal multiplies a quoted hourly or daily rate by an agreed quantity. Confirm whether the rate is for one person or a complete crew. If a quotation says “crew day,” do not multiply it by the crew size again. If it quotes each technician separately, keep those line items distinct.
A unit-based proposal multiplies a quoted price by a defined count or length. Clarify what counts as one unit: a weld, a measurement location, an image or an accepted inspection package. Determine whether difficult geometries, repeat visits and repair examinations use the same unit definition.
A fixed-price proposal is a single amount for its stated scope. It still needs an inclusion list and a process for changes. You can compare a fixed price with a time-based estimate, but record the uncertainty in the estimated duration. A forecast of three shifts is not the same commitment as an agreed three-shift maximum.
Our calculator deliberately avoids adding day-rate labour and a per-unit examination price automatically. Some contracts legitimately include both; others include the labour in the unit price. Only add a second charge when the quotation explicitly requires it.
Worked example: total a fictional supplier quote
Suppose a planning exercise uses a quoted crew rate of USD 1,400 per day for three days. Mobilisation is USD 600, separately supplied access is USD 900 and reporting is USD 300. These figures were selected solely to demonstrate the calculation. They are not evidence of what UT, RT or PAUT should cost in your city.
| Line item | Calculation | Example amount |
|---|---|---|
| Inspection work | 3 crew days × USD 1,400 | USD 4,200 |
| Mobilisation | Quoted lump sum | USD 600 |
| Access | Separately quoted allowance | USD 900 |
| Reporting | Separately quoted charge | USD 300 |
| Total entered scope | Sum of the four items | USD 6,000 |
This total excludes tax and anything not entered. If reporting is already included in the crew rate, set the separate reporting amount to zero; the example total becomes USD 5,700. If access is provided by the owner, decide whether it belongs in the supplier comparison, the owner's wider project budget or both as clearly distinguished records.
Now compare a fictional fixed-price offer of USD 5,800. It is only cheaper for the same purchase if its scope includes the same work and deliverables. An excluded access charge or a shorter permitted shift can reverse that comparison. The purpose of the worksheet is to expose those differences before a purchase order is issued.
Separate inspection cost from access and downtime
A crew rate does not describe the entire cost of an inspection campaign. Your project may require preparation, insulation removal, scaffolding, a lift, permits, cleaning or restoration. Specify which party supplies each item and whether it is ready before the inspection crew arrives.
Avoid using an unexplained multiplier such as “confined space equals twice the price.” Ask for the actual resource plan and charges applicable to the location. A supplier may price access directly, subcontract it or rely on owner-provided facilities. An arbitrary multiplier can hide that distinction and produce a misleading total.
Keep production downtime in a separate owner-cost calculation. It may matter greatly to the purchasing decision, but it is not automatically an invoice from the inspection provider. Compare schedule assumptions explicitly: the available window, coordination with other trades and the consequences of an interrupted visit.
Reporting and data handover belong in the RFQ
Specify the records you need before asking for a final price. A summary certificate, a marked-up drawing, encoded source files and a location-linked inspection history are different deliverables. Identify file formats, asset identifiers, delivery dates and the review process. State whether the client needs to reopen the source data in a particular system.
For digital radiography, our DICONDE handover guide describes questions for checking data exchange. For an asset model, the digital twin reporting guide explains how to test the connection between a finding, its location and the supporting report. NDT Connect is operated by Atlantis NDT; that guide identifies the related-company product feature.
Include the handling of incomplete coverage and inaccessible locations. A report should make limitations understandable. Ask how revisions are identified, who receives the final package and whether subsequent analysis is included. A low acquisition price can be less attractive if the required reporting work has not been priced.
Qualifications are a scope requirement, not a price badge
Request evidence that personnel and procedures meet the applicable customer and project requirements. Describe the method and task precisely rather than asking only for a generic “certified inspector.” Identify who is responsible for reviewing the qualification arrangements and whether the owner requires additional approval.
ASNT distinguishes employer-based certification from third-party certification. A certificate should be interpreted within its actual program and scope; it is not sufficient to treat every qualification label as interchangeable. ASNT: employer-based certification programs
Commercially, ask whether procedure preparation, demonstrations, witnessing or additional technical review are included. Do not assume a particular credential produces a fixed price premium. If a proposal includes specialist support, ask what deliverable that support provides and when it is required.
An RFQ checklist you can reuse
Send the same information to each prospective provider. If an item is unknown, label it unknown and ask the supplier to identify its pricing assumption. This is more useful than letting each bidder quietly fill the gap differently.
- Identify the site, country, currency, desired dates and contact for scope clarification.
- List assets, component quantities, dimensions, materials and available drawings.
- State the examination objective, applicable requirements and required acceptance basis.
- Describe access, surface preparation, working windows and owner-provided support.
- Identify required personnel qualifications and any owner approval process.
- List reports, source data, location references, review stages and delivery deadlines.
- Request the billing unit, minimum charge, included crew and equipment, and estimated quantity.
- Separate mobilisation, travel, access, reporting, standby and other quoted extras.
- Ask how repeat examinations, repairs, cancellation and scope changes are charged.
- Record quote validity, exclusions and the party responsible for each assumption.
Keep the original quotation alongside your comparison sheet. If a clarification changes the scope, ask for a revised written proposal or a clear written amendment. Record that revision in every bid comparison so a later decision is based on the same information.
Turn a budget into a comparable purchase
Start with a technically suitable scope, collect written rates and normalize their inclusions. Use the quote calculator to check arithmetic, then have the responsible team resolve technical and commercial differences. The tool does not predict site productivity or determine whether a method is acceptable.
When you are ready to approach providers, prepare an inspection request or browse the provider directory. Include enough scope detail for a meaningful response. Better information at the beginning makes the resulting price list easier to compare and the eventual inspection package easier to use.
Common questions
Is there a standard NDT inspection price list?
There is no universal price list established by this guide. A useful price comparison requires the same scope, billing unit, crew, equipment, access, reporting and exclusions. Request written rates for your project.
How do I calculate an NDT inspection quote?
Multiply the quoted rate by the quoted quantity for one billing basis, then add separately priced mobilisation, access, reporting and other extras. Do not add both a day rate and a per-weld rate unless the supplier explicitly bills both.
Does a PAUT quote automatically cost more than an RT quote?
No general price ranking can be established without comparable scopes. Compare the accepted examination, coverage, site restrictions, reporting and total project cost, not just the instrument or crew rate.